Construction Updates – September 17, 2025
Posted on Wednesday, September 17, 2025 01:00 PM
New Aquatics Facility Project
More information on the New Aquatics Facility Project
- Design and construction team has been selected
- Design work is underway
- Detailed design is underway and is expected to be completed in April 2026
JRC (Jubilee Recreation Centre) Modernization
More information on the JRC Modernization project
- The Jubilee Recreation Centre is open
- Deficiencies are being addressed
Local Road Rehabilitation Program
Local Road Rehabilitation is an annual program that prioritizes road repairs...
Construction Updates – September 3, 2025
Posted on Wednesday, September 03, 2025 01:40 PM
New Aquatics Facility Project
More information on the New Aquatics Facility Project
- Design and construction team has been selected
- Design work is underway
- Detailed design is underway and is expected to be completed in April 2026
2025 Sump Pump Retro Fit Program – Sonora Crescent
- This is a multi-year program, connecting residential sump pumps to the underground infrastructure collection system
- Construction is complete
- Deficiencies are being addressed
Bike Skills Park
- Budget consideration for construction...
Construction Updates – August 20, 2025
Posted on Wednesday, August 20, 2025 03:10 PM
New Aquatics Facility Project
More information on the New Aquatics Facility Project
- Design and construction team has been selected
- Design work is underway
- The second and third reading of the borrowing bylaw was approved
- Detailed design will occur from September 2025 to April 2026
2025 Sump Pump Retro Fit Program – Sonora Crescent
- This is a multi-year program, connecting residential sump pumps to the underground infrastructure collection system
- Construction is complete
- Deficiencies are being addressed
Construction Updates – August 6, 2025
Posted on Wednesday, August 06, 2025 03:36 PM
New Aquatics Facility Project
More information on the New Aquatics Facility Project
- Design and construction team has been selected
- Design work is underway
- Construction budget was approved by Council on July 8, 2025
- The second and third reading of the borrowing bylaw will occur August 12, 2025
2025 Sump Pump Retro Fit Program – Sonora Crescent
- This is a multi-year program, connecting residential sump pumps to the underground infrastructure collection system
- Construction is underway
Bike Skills Park
- Budget...
Construction Updates – July 23, 2025
Posted on Wednesday, July 23, 2025 03:47 PM
New Aquatics Facility Project
More information on the New Aquatics Facility Project
- Design and construction team has been selected
- Design work is underway
- Construction budget was approved by Council on July 8, 2025
- The second and third reading of the borrowing bylaw will occur in August 2025
2025 Sump Pump Retro Fit Program – Sonora Crescent
- This is a multi-year program, connecting residential sump pumps to the underground infrastructure collection system
- Construction is underway
Bike Skills Park
- Design...