Construction Updates – October 20, 2022
Posted on Thursday, October 20, 2022 08:50 AM
94 Street Road Widening
- 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
- Sidewalks are complete
- Curb and gutter is complete for new lanes
- Work on the concrete for the center median is complete
- Final paving is occurring the week of October 17
- Landscaping is complete
- Work includes concrete bump outs at Greenfield Link and Dillingham Ave, raised crosswalks and flashing crosswalk lights
- Work is complete except...
Construction Updates – October 11, 2022
Posted on Tuesday, October 11, 2022 10:56 AM
94 Street Road Widening
- 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
- Sidewalks are complete
- Curb and gutter is complete for new lanes
- Work on the concrete for the center medians is underway
- Final paving will occur the week of October 10
- Landscaping is complete
- New flashing cross walk signs and lights are installed at all locations for 2022
- Map of Crosswalk Improvement Locations
Construction Updates – September 22, 2022
Posted on Thursday, September 22, 2022 11:42 AM
94 Street Road Widening
- 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
- Sidewalks are complete
- Curb and gutter is complete for new lanes
- Paving for the new lanes is complete. The final lift of asphalt will be placed once the center medians are complete.
- Work on the concrete for the center medians is underway
- New flashing crosswalk signs and lights are installed, except for Greenfield Way. The crosswalk lights on...
Construction Updates – September 6, 2022
Posted on Tuesday, September 06, 2022 01:38 PM
94 Street Road Widening
- 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
- Sidewalks are complete
- Curb and gutter is complete for new lanes
- Paving for the new lanes is scheduled for the week of September 5. Once paving is complete for the new lanes traffic will switch over so the concrete medians can be completed.
- New flashing crosswalk signs and lights are installed, except for Greenfield Way. The crosswalk...
Construction Updates – August 23, 2022
Posted on Tuesday, August 23, 2022 12:07 PM
94 Street Road Widening
- 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
- Sidewalks are complete
- Subgrade work for the road is complete. Gravel is being placed.
- Curb and gutter is complete for new lanes
- Paving for new lane is expected to occur week of August 29. Once paving is complete for the new lanes traffic will switch over, so concrete medians can be completed
- New flashing cross walk signs and lights are...