Construction Updates – February 6, 2025
Posted on Thursday, February 06, 2025 08:57 AM
New Aquatics Facility Project
More information on the New Aquatics Facility Project
- Design and construction team has been selected
- Design work has started
Bike Skills Park
- Design a bike skills park in the West River’s Edge area
- Request for Proposal (RFP) has been posted
- The RFP will close on March 4, 2025
Disc Golf Course
- Design and construct a 9-hole disc golf course in the West River’s Edge area
- Request for Proposal (RFP) has been posted
- The RFP will close on March 4, 2025
Heritage Trails Park (Fort...
Construction Updates – January 30, 2025
Posted on Thursday, January 30, 2025 10:19 AM
New Aquatics Facility Project
More information on the New Aquatics Facility Project
- Design and construction team has been selected
- Design work has started
Heritage Trails Park (Fort Centre Park) – Landscaping Phase 1
More information on the Heritage Trails Park project
- Fort Centre Park was renamed to Heritage Trails Park on July 2, 2024
- Construction is complete for the season
- Deficiencies will be addressed in Spring 2025
JRC (Jubilee Recreation Centre) Modernization
More information on the JRC...
Construction Updates – January 8, 2025
Posted on Wednesday, January 08, 2025 10:33 AM
New Aquatics Facility Project
More information on the New Aquatics Facility Project
- Design and construction team has been selected
- Design work to begin in January 2025
Heritage Trails Park (Fort Centre Park) – Landscaping Phase 1
More information on the Heritage Trails Park project
- Fort Centre Park was renamed to Heritage Trails Park on July 2, 2024
- Construction is complete for the season
- Deficiencies will be addressed in Spring 2025
JRC (Jubilee Recreation Centre) Modernization
Construction Updates – December 18, 2024
Posted on Wednesday, December 18, 2024 12:37 PM
Aquatics Planning and Construction
- The Request for Proposal (RFP) for an Integrated Project Delivery Team for Aquatics Planning and Construction was posted
- The RFP closed and design and construction team has been selected
- Design work to begin in January 2025
Heritage Trails Park (Fort Centre Park) – Landscaping Phase 1
More information on the Heritage Trails Park project
- Fort Centre Park was renamed to Heritage Trails Park on July 2, 2024
- Construction is complete for the season
- Deficiencies will be...
Construction Updates – December 4, 2024
Posted on Wednesday, December 04, 2024 04:30 PM
Aquatics Planning and Construction
- The Request for Proposal (RFP) for an Integrated Project Delivery Team for Aquatics Planning and Construction was posted
- The RFP closed and proposals are being evaluated
Heritage Trails Park (Fort Centre Park) – Landscaping Phase 1
More information on the Heritage Trails Park project
- Fort Centre Park was renamed to Heritage Trails Park on July 2, 2024
- Construction is complete for the season
- Deficiencies will be address in the spring of 2025
JRC (Jubilee Recreation...