Construction Updates – November 2, 2022

Posted on Wednesday, November 02, 2022 10:19 AM

94 Street Road Widening

  • 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
  • Project is complete except for some minor deficiencies
Greenfield Way Traffic Calming
  • Work includes concrete bump outs at Greenfield Link and Dillingham Ave, raised crosswalks and flashing crosswalk lights
  • Line painting will be complete in November, depending on weather. Remaining signage will be installed in early November.
Highway 15 Bridge Twinning
  • Alberta...

Construction Updates – October 20, 2022

Posted on Thursday, October 20, 2022 08:50 AM

94 Street Road Widening

  • 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
  • Sidewalks are complete
  • Curb and gutter is complete for new lanes
  • Work on the concrete for the center median is complete
  • Final paving is occurring the week of October 17
  • Landscaping is complete
Greenfield Way Traffic Calming
  • Work includes concrete bump outs at Greenfield Link and Dillingham Ave, raised crosswalks and flashing crosswalk lights
  • Work is complete except...

Construction Updates – October 11, 2022

Posted on Tuesday, October 11, 2022 10:56 AM

94 Street Road Widening

  • 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
  • Sidewalks are complete
  • Curb and gutter is complete for new lanes
  • Work on the concrete for the center medians is underway
  • Final paving will occur the week of October 10
  • Landscaping is complete
Crosswalk Improvements Greenfield Way Traffic Calming

Construction Updates – September 22, 2022

Posted on Thursday, September 22, 2022 11:42 AM

94 Street Road Widening

  • 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
  • Sidewalks are complete
  • Curb and gutter is complete for new lanes
  • Paving for the new lanes is complete. The final lift of asphalt will be placed once the center medians are complete.
  • Work on the concrete for the center medians is underway
Crosswalk Improvements
  • New flashing crosswalk signs and lights are installed, except for Greenfield Way. The crosswalk lights on...

Construction Updates – September 6, 2022

Posted on Tuesday, September 06, 2022 01:38 PM

94 Street Road Widening

  • 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
  • Sidewalks are complete
  • Curb and gutter is complete for new lanes
  • Paving for the new lanes is scheduled for the week of September 5. Once paving is complete for the new lanes traffic will switch over so the concrete medians can be completed.
Crosswalk Improvements
  • New flashing crosswalk signs and lights are installed, except for Greenfield Way. The crosswalk...