Construction Updates – August 23, 2022

Posted on Tuesday, August 23, 2022 12:07 PM

94 Street Road Widening

  • 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
  • Sidewalks are complete
  • Subgrade work for the road is complete. Gravel is being placed.
  • Curb and gutter is complete for new lanes
  • Paving for new lane is expected to occur week of August 29. Once paving is complete for the new lanes traffic will switch over, so concrete medians can be completed
Crosswalk Improvements
  • New flashing cross walk signs and lights are...

Construction Updates – August 9, 2022

Posted on Tuesday, August 09, 2022 02:05 PM

94 Street Road Widening

  • 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
  • Storm infrastructure is installed
  • Sidewalks are complete
  • Subgrade work for the road is complete. Gravel is being placed.
  • Work on the curb and gutter will start the week of August 15
Crosswalk Improvements Greenfield Way Traffic Calming
  • Detailed...

Construction Updates – July 13, 2022

Posted on Wednesday, July 13, 2022 02:26 PM

94 Street Road Widening

  • 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
  • Storm infrastructure is installed
  • Subgrade work for the sidewalk is complete
  • Subgrade work for the road is underway
Highway 15 Bridge Twinning
  • Alberta Transportation is leading this project
  • Work continues on the west side of the North Saskatchewan River
  • Work is underway on the portion of Hwy 15 within the City of Fort Saskatchewan limits. Fort Centre Park Trail...

Construction Updates – June 30, 2022

Posted on Thursday, June 30, 2022 10:10 AM

94 Street Road Widening

  • 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
  • The contractor has mobilized to site and work is underway
  • Storm infrastructure is installed
  • Subgrade work for the sidewalk is complete
  • Subgrade work for the road is underway
Highway 15 Bridge Twinning
  • Alberta Transportation is leading this project
  • Work continues on the west side of the North Saskatchewan River
  • Work is underway on the portion of Hwy 15 within the...

Construction Updates – June 14, 2022

Posted on Tuesday, June 14, 2022 11:03 AM

94 Street Road Widening

  • 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
  • The contractor has mobilized to site and work is underway
  • The contractor has removed the top soil and has started grading work
  • The contractor is working on underground storm utilities
  • The contractor is working on subgrade preparation for the sidewalk
Highway 15 Bridge Twinning
  • Alberta Transportation is leading this project
  • Work continues on the west side of the...