Construction Updates – May 22, 2024
Posted on Wednesday, May 22, 2024 02:00 PM
100 Avenue Road Enhancements (Legacy Park)
- Tender is posted and closes on June 14, 2024
- Construction to begin in Summer 2024, after Canada Day
2024 Local Road Rehabilitation Program
- Tender for construction closed and has been awarded
- Construction to start the week of June 10, 2024
2024 Pedestrian Activated Crosswalk Flashing Lights
- Contract has been awarded
- 2024 Pedestrian Activated Crosswalk Flashing Lights Locations Map
2024 Sump Pump Retrofit Program – Catalina Court
- Construction to begin in July 2024
Construction Updates – April 24, 2024
Posted on Wednesday, April 24, 2024 02:00 PM
100 Avenue Road Enhancements (Legacy Park)
- Design is underway
- Construction to begin in Summer 2024, after Canada Day
2024 Local Road Rehabilitation Program
- Tender for construction is posted and closes on April 30, 2024
2024 Sump Pump Retrofit Program – Catalina Court
- Construction to begin in Summer 2024
Fort Centre Park – Landscaping Phase 1
- Contractor has been selected
- Construction to begin in May 2024
JRC (Jubilee Recreation Centre) Modernization
More information on the JRC Modernization project
- The...
Construction Updates – April 10, 2024
Posted on Wednesday, April 10, 2024 11:25 AM
100 Avenue Road Enhancements (Legacy Park)
- Design is underway
- Construction to begin in Summer 2024, after Canada Day
2024 Local Road Rehabilitation Program
- Tender for construction is posted and closes on April 30, 2024
2024 Sump Pump Retrofit Program – Catalina Court
- Construction to begin in Summer 2024
Fort Centre Park – Landscaping Phase 1
- Contractor has been selected
- Construction to begin in May 2024
JRC (Jubilee Recreation Centre) Modernization
More information on the JRC Modernization project
- The...
Construction Updates – March 28, 2024
Posted on Thursday, March 28, 2024 03:07 PM
100 Avenue Road Enhancements (Legacy Park)
- Design is underway
2024 Sump Pump Retrofit Program – Catalina Court
- Construction to begin in Summer 2024
Fort Centre Park – Landscaping Phase 1
- Tender closed and bids are being evaluated
JRC (Jubilee Recreation Centre) Modernization
More information on the JRC Modernization project
- The temporary facilities are open
- Work is continuing on foundations at the front of the building
- The remaining lower level concrete slab will be poured by end of March 2024
- Work is...
Construction Updates – March 13, 2024
Posted on Wednesday, March 13, 2024 10:57 AM
100 Avenue Road Enhancements (Legacy Park)
- Design is underway
2024 Sump Pump Retrofit Program
- Tender for construction closed February 20, 2024
- Contractor has been selected
Fort Centre Park – Landscaping Phase 1
- Tender for construction is posted, closing March 26, 2024
JRC (Jubilee Recreation Centre) Modernization
More information on the JRC Modernization project
- The temporary facilities are open
- Work is continuing on foundations at the front of the building
- The lower level concrete slab will be poured the...