Construction Updates – October 18, 2023

Posted on Wednesday, October 18, 2023 09:44 AM

92 Street Trail Improvement

  • Converting 92 Street from Dillingham Avenue to Meadowview Drive to a pedestrian and cyclist trail
  • The new asphalt trail is paved
  • Landscaping work is underway
Fort Centre Park – Phase 1
  • Installation of stormwater piping is complete
JRC (Jubilee Recreation Centre) Modernization

More information on the JRC Modernization project

  • Installation of deep utilities is underway
  • Hazardous material remediation and demolition is underway
  • The temporary facilities are open
Neighbourhood...

Construction Updates – October 10, 2023

Posted on Tuesday, October 10, 2023 10:35 AM

92 Street Trail Improvement

  • Converting 92 Street from Dillingham Avenue to Meadowview Drive to a pedestrian and cyclist trail
  • The new asphalt trail is paved
  • Landscaping work is underway
Fort Centre Park – Phase 1
  • Installation of stormwater piping is complete
JRC (Jubilee Recreation Centre) Modernization

More information on the JRC Modernization project

  • Installation of deep utilities is underway
  • Hazardous material remediation and demolition is underway
  • The temporary facilities are open
Neighbourhood...

Construction Updates – September 26, 2023

Posted on Tuesday, September 26, 2023 10:33 AM

92 Street Trail Improvement

  • Converting 92 Street from Dillingham Avenue to Meadowview Drive to a pedestrian and cyclist trail
  • The new asphalt trail is paved
  • Landscaping work is underway
Fort Centre Park – Phase 1
  • Installation of stormwater piping has begun and will be completed by fall, subject to weather conditions
JRC (Jubilee Recreation Centre) Modernization

More information on the JRC Modernization project

  • Installation of deep utilities is underway
  • Hazardous material remediation and demolition is...

Construction Updates – September 12, 2023

Posted on Tuesday, September 12, 2023 10:10 AM

92 Street Trail Improvement

  • Converting 92 Street from Dillingham Avenue to Meadowview Drive to a pedestrian and cyclist trail
  • Grading work is complete
  • The new asphalt trail is underway
Fort Centre Park – Phase 1
  • Installation of stormwater piping has begun and will be completed by fall, subject to weather conditions
JRC (Jubilee Recreation Centre) Modernization

More information on the JRC Modernization project

  • Installation of deep utilities is underway
  • Hazardous material remediation is underway
  • The...

Construction Updates – August 29, 2023

Posted on Tuesday, August 29, 2023 10:37 AM

92 Street Trail Improvement

  • Converting 92 Street from Dillingham Avenue to Meadowview Drive to a pedestrian and cyclist trail
  • Grading work is complete
  • The new asphalt trail is underway
Fort Centre Park – Phase 1
  • Installation of stormwater piping has begun and will be completed by fall, subject to weather conditions
Highway 15 Bridge Twinning
  • Alberta Transportation is leading this project
  • Landscaping near the pedestrian bridge is underway
JRC (Jubilee Recreation Centre) Modernization

More information on...