Construction Updates – September 12, 2023

Posted on Tuesday, September 12, 2023 10:10 AM

92 Street Trail Improvement

  • Converting 92 Street from Dillingham Avenue to Meadowview Drive to a pedestrian and cyclist trail
  • Grading work is complete
  • The new asphalt trail is underway
Fort Centre Park – Phase 1
  • Installation of stormwater piping has begun and will be completed by fall, subject to weather conditions
JRC (Jubilee Recreation Centre) Modernization

More information on the JRC Modernization project

  • Installation of deep utilities is underway
  • Hazardous material remediation is underway
  • The...

Construction Updates – August 29, 2023

Posted on Tuesday, August 29, 2023 10:37 AM

92 Street Trail Improvement

  • Converting 92 Street from Dillingham Avenue to Meadowview Drive to a pedestrian and cyclist trail
  • Grading work is complete
  • The new asphalt trail is underway
Fort Centre Park – Phase 1
  • Installation of stormwater piping has begun and will be completed by fall, subject to weather conditions
Highway 15 Bridge Twinning
  • Alberta Transportation is leading this project
  • Landscaping near the pedestrian bridge is underway
JRC (Jubilee Recreation Centre) Modernization

More information on...

Construction Updates – August 1, 2023

Posted on Tuesday, August 01, 2023 11:34 AM

92 Street Trail Improvement

  • Converting 92 Street from Dillingham Avenue to Meadowview Drive to a pedestrian and cyclist trail
  • Grading work is underway
Fort Centre Park – Phase 1
  • Installation of stormwater piping has begun and will be completed by early fall, subject to weather conditions
Highway 15 Bridge Twinning
  • Alberta Transportation is leading this project
  • Work is complete on the portion of Hwy 15 within the City of Fort Saskatchewan limits
  • Paving of the trails is complete
  • Landscaping near the...

Construction Updates – July 18, 2023

Posted on Tuesday, July 18, 2023 11:17 AM

Fort Centre Park – Phase 1

  • Installation of stormwater piping has begun and will be completed by end of July, subject to weather conditions
Highway 15 Bridge Twinning
  • Alberta Transportation is leading this project
  • Work is complete on the portion of Hwy 15 within the City of Fort Saskatchewan limits
  • Paving of the trails is complete
  • Landscaping near the trails is to begin in July
  • Pedestrian bridge over the North Saskatchewan River is closed
JRC (Jubilee Recreation Centre) Modernization

More information on...

Construction Updates – July 5, 2023

Posted on Wednesday, July 05, 2023 10:41 AM

Fort Centre Park – Phase 1

  • Installation of stormwater piping has begun and will be completed by end of July, subject to weather conditions
Highway 15 Bridge Twinning
  • Alberta Transportation is leading this project
  • Work is complete on the portion of Hwy 15 within the City of Fort Saskatchewan limits
  • Paving of the trails is complete
  • Pedestrian bridge over the North Saskatchewan River is closed
JRC (Jubilee Recreation Centre) Modernization

More information on the JRC Modernization project

  • Design work is...