Construction Updates – August 28, 2024
Posted on Wednesday, August 28, 2024 02:37 PM
100 Avenue Road Enhancements (Legacy Park)
- Road is being paved
- Landscaping to begin the first week of September 2024
- 100 Avenue (Legacy Park) Closure & Parking Map
2024 Local Road Rehabilitation Program
- Night paving on Highway 15 is underway
- 2024 Local Road Rehabilitation Program Map
2024 Sump Pump Retrofit Program – Catalina Court
- Construction is complete
- Deficiencies are being addressed
Heritage Trails Park (Fort Centre Park) – Landscaping Phase 1
More information on the Heritage Trails Park project
- Fort...
Construction Updates – August 14, 2024
Posted on Wednesday, August 14, 2024 03:26 PM
100 Avenue Road Enhancements (Legacy Park)
- Construction is underway
- 100 Avenue (Legacy Park) Closure & Parking Map
2024 Local Road Rehabilitation Program
- Construction is underway
- 2024 Local Road Rehabilitation Program Map
2024 Sump Pump Retrofit Program – Catalina Court
- Construction is underway
Heritage Trails Park (Fort Centre Park) – Landscaping Phase 1
More information on the Heritage Trails Park project
- Fort Centre Park was renamed to Heritage Trails Park on July 2, 2024
- Construction is underway
- Site...
Construction Updates – July 31, 2024
Posted on Thursday, August 01, 2024 10:28 AM
100 Avenue Road Enhancements (Legacy Park)
- Construction is underway
- 100 Avenue (Legacy Park) Closure & Parking Map
2024 Local Road Rehabilitation Program
- Construction is underway
- 2024 Local Road Rehabilitation Program Map
2024 Pedestrian Activated Crosswalk Flashing Lights
- Installation is complete
- 2024 Pedestrian Activated Crosswalk Flashing Lights Locations Map
2024 Sump Pump Retrofit Program – Catalina Court
- Construction has begun
Fort Centre Park – Landscaping Phase 1
More information on the Fort Centre...
Construction Updates – July 17, 2024
Posted on Wednesday, July 17, 2024 10:53 AM
100 Avenue Road Enhancements (Legacy Park)
- Construction to begin in late July 2024
- 100 Avenue (Legacy Park) Closure & Parking Map
2024 Local Road Rehabilitation Program
- Construction is underway
- 2024 Local Road Rehabilitation Program Map
2024 Pedestrian Activated Crosswalk Flashing Lights
- Installation to start by the end of July 2024
- 2024 Pedestrian Activated Crosswalk Flashing Lights Locations Map
2024 Sump Pump Retrofit Program – Catalina Court
- Construction has begun
Fort Centre Park – Landscaping Phase...
Construction Updates – July 9, 2024
Posted on Tuesday, July 09, 2024 08:43 AM
100 Avenue Road Enhancements (Legacy Park)
- Tender has been awarded
- Construction to begin in late July 2024
2024 Local Road Rehabilitation Program
- Construction has started
- 2024 Local Road Rehabilitation Program Map
2024 Pedestrian Activated Crosswalk Flashing Lights
- Installation to start by the end of July 2024
- 2024 Pedestrian Activated Crosswalk Flashing Lights Locations Map
2024 Sump Pump Retrofit Program – Catalina Court
- Construction has begun
Fort Centre Park – Landscaping Phase 1