Construction Updates – March 6, 2025

Posted on Thursday, March 06, 2025 09:51 AM

New Aquatics Facility Project

More information on the New Aquatics Facility Project

  • Design and construction team has been selected
  • Design work has started
  • The Public Survey closed March 5, 2025. Results of the survey will be presented to City Council on April 8, 2025.
     

2025 Sump Pump Retro Fit Program – Sonora Crescent
  • Tender for construction is posted
  • Tender for construction closes April 1, 2025
     

Bike Skills Park
  • Design a bike skills park in the West River’s Edge area
  • The RFP has closed. Submissions are...





Construction Updates – February 19, 2025

Posted on Wednesday, February 19, 2025 11:08 AM

New Aquatics Facility Project

More information on the New Aquatics Facility Project

  • Design and construction team has been selected
  • Design work has started
  • Public Survey regarding amenities is posted. People can complete the survey between February 18 and March 05, 2025.

Bike Skills Park
  • Design a bike skills park in the West River’s Edge area
  • Request for Proposal (RFP) has been posted
  • The RFP will close on March 4, 2025
     

Disc Golf Course
  • Design and construct a...




Construction Updates – February 6, 2025

Posted on Thursday, February 06, 2025 08:57 AM

New Aquatics Facility Project

More information on the New Aquatics Facility Project

  • Design and construction team has been selected
  • Design work has started
     

Bike Skills Park
  • Design a bike skills park in the West River’s Edge area
  • Request for Proposal (RFP) has been posted
  • The RFP will close on March 4, 2025
     

Disc Golf Course
  • Design and construct a 9-hole disc golf course in the West River’s Edge area
  • Request for Proposal (RFP) has been posted
  • The RFP will close on March 4, 2025
     

Heritage Trails Park (Fort...


Construction Updates – January 30, 2025

Posted on Thursday, January 30, 2025 10:19 AM

New Aquatics Facility Project

More information on the New Aquatics Facility Project

  • Design and construction team has been selected
  • Design work has started
     

Heritage Trails Park (Fort Centre Park) – Landscaping Phase 1

More information on the Heritage Trails Park project

  • Fort Centre Park was renamed to Heritage Trails Park on July 2, 2024
  • Construction is complete for the season
  • Deficiencies will be addressed in Spring 2025
      

JRC (Jubilee Recreation Centre) Modernization

More information on the JRC...



Construction Updates – January 8, 2025

Posted on Wednesday, January 08, 2025 10:33 AM

New Aquatics Facility Project

More information on the New Aquatics Facility Project

  • Design and construction team has been selected
  • Design work to begin in January 2025
     

Heritage Trails Park (Fort Centre Park) – Landscaping Phase 1

More information on the Heritage Trails Park project

  • Fort Centre Park was renamed to Heritage Trails Park on July 2, 2024
  • Construction is complete for the season
  • Deficiencies will be addressed in Spring 2025
      

JRC (Jubilee Recreation Centre) Modernization

More information on the...