Construction Updates – March 6, 2025
Posted on Thursday, March 06, 2025 09:51 AM
New Aquatics Facility Project
More information on the New Aquatics Facility Project
- Design and construction team has been selected
- Design work has started
- The Public Survey closed March 5, 2025. Results of the survey will be presented to City Council on April 8, 2025.
2025 Sump Pump Retro Fit Program – Sonora Crescent
- Tender for construction is posted
- Tender for construction closes April 1, 2025
Bike Skills Park
- Design a bike skills park in the West River’s Edge area
- The RFP has closed. Submissions are...
Construction Updates – February 19, 2025
Posted on Wednesday, February 19, 2025 11:08 AM
New Aquatics Facility Project
More information on the New Aquatics Facility Project
- Design and construction team has been selected
- Design work has started
- Public Survey regarding amenities is posted. People can complete the survey between February 18 and March 05, 2025.
- Take the survey at fortsask.ca/AquaticsSurvey
- Take the survey at fortsask.ca/AquaticsSurvey
Bike Skills Park
- Design a bike skills park in the West River’s Edge area
- Request for Proposal (RFP) has been posted
- The RFP will close on March 4, 2025
Disc Golf Course
- Design and construct a...
Construction Updates – February 6, 2025
Posted on Thursday, February 06, 2025 08:57 AM
New Aquatics Facility Project
More information on the New Aquatics Facility Project
- Design and construction team has been selected
- Design work has started
Bike Skills Park
- Design a bike skills park in the West River’s Edge area
- Request for Proposal (RFP) has been posted
- The RFP will close on March 4, 2025
Disc Golf Course
- Design and construct a 9-hole disc golf course in the West River’s Edge area
- Request for Proposal (RFP) has been posted
- The RFP will close on March 4, 2025
Heritage Trails Park (Fort...
Construction Updates – January 30, 2025
Posted on Thursday, January 30, 2025 10:19 AM
New Aquatics Facility Project
More information on the New Aquatics Facility Project
- Design and construction team has been selected
- Design work has started
Heritage Trails Park (Fort Centre Park) – Landscaping Phase 1
More information on the Heritage Trails Park project
- Fort Centre Park was renamed to Heritage Trails Park on July 2, 2024
- Construction is complete for the season
- Deficiencies will be addressed in Spring 2025
JRC (Jubilee Recreation Centre) Modernization
More information on the JRC...
Construction Updates – January 8, 2025
Posted on Wednesday, January 08, 2025 10:33 AM
New Aquatics Facility Project
More information on the New Aquatics Facility Project
- Design and construction team has been selected
- Design work to begin in January 2025
Heritage Trails Park (Fort Centre Park) – Landscaping Phase 1
More information on the Heritage Trails Park project
- Fort Centre Park was renamed to Heritage Trails Park on July 2, 2024
- Construction is complete for the season
- Deficiencies will be addressed in Spring 2025
JRC (Jubilee Recreation Centre) Modernization