Construction Updates
Search
Construction Updates – June 14, 2022
Posted on Tuesday, June 14, 2022 11:03 AM
94 Street Road Widening
- 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
- The contractor has mobilized to site and work is underway
- The contractor has removed the top soil and has started grading work
- The contractor is working on underground storm utilities
- The contractor is working on subgrade preparation for the sidewalk
Highway 15 Bridge Twinning
- Alberta Transportation is leading this project
- Work continues on the west side...
Construction Updates – May 31, 2022
Posted on Tuesday, May 31, 2022 11:03 AM
94 Street Road Widening
- 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
- The contractor has mobilized to site and work is underway
- The contractor has removed the top soil and has started grading work
Highway 15 Bridge Twinning
- Alberta Transportation is leading this project
- Work continues on the west side of the North Saskatchewan River
- Work is underway on the portion of Hwy 15 within the City of Fort Saskatchewan limits. Fort...
Construction Updates – May 18, 2022
Posted on Wednesday, May 18, 2022 10:57 AM
94 Street Road Widening
- 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
- The tender closed and a contractor has been selected
- Work is scheduled to start in June
Highway 15 Bridge Twinning
- Alberta Transportation is leading this project
- Work continues on the west side of the North Saskatchewan River
- Work is underway on the portion of Hwy 15 within the City of Fort Saskatchewan limits. Fort Centre Park Trail Closures in effect...
Construction Updates – May 11, 2022
Posted on Wednesday, May 11, 2022 04:31 PM
94 Street Road Widening
- 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
- The tender closed and a contractor has been selected
- Work is scheduled to start in June
Highway 15 Bridge Twinning
- Alberta Transportation is leading this project
- Work continues on the west side of the North Saskatchewan River
- Work is underway on the portion of Hwy 15 within the City of Fort Saskatchewan limits. Fort Centre Park Trail Closures in effect...
Construction Updates – April 20, 2022
Posted on Wednesday, April 20, 2022 10:35 AM
94 Street Road Widening
- 94 Street from Southfort Drive to approximately 300m south of the Hospital is being widened from 2 lanes to 4 lanes
- The tender closed and a contractor has been selected
- Work is expected to start in June
Highway 15 Bridge Twinning
- Alberta Transportation is leading this project
- Work continues on the west side of the North Saskatchewan River
- Work is underway on the portion of Hwy 15 within the City of Fort Saskatchewan limits. Fort Centre Park Trail Closures in effect...