August 4, 2020 Updates

Posted On Tuesday August 04, 2020

The City of Fort Saskatchewan endeavours to keep residents and visitors up-to-date about ongoing City construction projects.

For further information please call 780-992-6248.

112th Street Widening

  • Design is complete
  • Tender is posted and closes August 13 @ 2pm
  • Construction is scheduled to start in late August

Bulk Water Modernization

  • Design is underway and construction to take place this summer
  • Tender has closed and bids are being evaluated

City Hall Lower Level

  • The lower level at City Hall is being developed into office space
  • Work is starting the week of August 3rd

Dog Kennel

  • Dog Kennel will be located at the Protective Services Building
  • Underground services to the building are complete
  • Work on the foundation is complete
  • Framing of the building is complete
  • Interior and exterior finishing work is underway
  • Work is expected to be complete in August

Gymnastics Centre Parking Lot

  • Tender to rehabilitate the Gymnastics Centre parking lot is posted and closes August 14th

Hwy 15 & 119 Street Intersection

  • Design is being finalized and construction to take place this summer
  • Tender has closed and bids are being evaluated

Highway 15 Bridge Twinning

  • Alberta Transportation is leading this project
  • Work continues on the west side of the North Saskatchewan River
  • Work is underway on the portion of Hwy 15 within the City of Fort Saskatchewan limits.
  • Fort Centre Park Trail Closures in effect August 26, 2019 - October 1, 2022

Local Road Rehab

  • Project locations for the 2020 Local Road Rehab program have been finalized.
  • All locations have been completed except for 101 Street between 88 Ave and 86 Ave. Concrete work is complete and paving is expected to occur the week of August 3rd

Neighbourhood Rehab – 101 Street

  • Work to replace water, sewer and road infrastructure from 101 Ave to 99 Ave
  • Work has been deferred to 2021

Neighbourhood Rehab – 108 Street

  • Design work to replace water, sewer and road infrastructure on 108 Street from 101 Ave to the end of 108 Street will start in 2020. Construction is scheduled for 2021.

Old Gaol Bridge Rail Replacement

  • Tender is posted for a contractor to replace the railing on the Old Gaol Bridge. The project has been awarded.
  • Work is expected to start in September

Pointe Aux Pins Road Widening

  • The project will widen Point Aux Pins road from Wilshire Blvd to Range Road 231. This will bring the road up to the City’s urban standard and provide an asphalt trail on the north side of the road.
  • Design work is complete
  • Tender for construction is closed and bids are being evaluated

Sportsplex Ice Plant Replacement

  • Contractor has been hired to replace the ice plant. Work scheduled to take place in August
  • Tender for room modifications to the ice plant room is posted and closes August 11th

Southview Way Road Extension

  • Southview Way is located between Heartland Ford and the future Fire Hall. The road will be extended approximately 120m to the South
  • Surface work is complete
  • Street lights and landscaping work will be completed in August

Sump Pump Retrofit Program

  • Work has been deferred to 2021

Veterans Way Corridor Widening

  • Design work to widen the first section of the Veterans Way Corridor from 4 lanes to 6 lanes will take place in 2020.