October 16, 2020 Updates

Posted On Friday October 16, 2020

The City of Fort Saskatchewan endeavours to keep residents and visitors up-to-date about ongoing City construction projects.

For further information please call 780-992-6248.


93rd Ave and Sherridon Drive Alley – Water Valve Replacement

 •  Work to replace valves and hydrants in the alley behind 93rd Ave and Sherridon Drive is expected to start in early October. Notices to affected residents are being delivered with additional information.


112th Street Widening

 •  112th Street from 108 St to Hwy 15 will be closed starting September 19. The closure will remain for the duration of construction, which is scheduled to be complete by the end of October.
 •  Stripping and grading is underway
 •  Installation of storm infrastructure has started
 •  Concrete work is expected to start the week of October 12th
 •  View 112th Street Closure Map


City Hall Lower Level

 •  The lower level at City Hall is being developed into office space
 •  Framing is completed and electrical rough-ins are underway along with plumbing and HVAC work. Drywall will follow.


Dog Kennel

 •  Dog Kennel will be located at the Protective Services Building
 •  Interior and exterior finishing work is complete. Deficiencies will be addressed over the next few weeks.


Gymnastics Centre Parking Lot

 •  Work has started and is expected to be complete in October
 •  Installation of storm infrastructure is complete
 •  Concrete work is scheduled to take place the week of October 12th


Hwy 15 & 119 Street Intersection

 •  Design is complete and construction to start in September
 •  Tender has closed and a contractor has been selected


Highway 15 Bridge Twinning

 •  Alberta Transportation is leading this project
 •  Work continues on the west side of the North Saskatchewan River
 •  Work is underway on the portion of Hwy 15 within the City of Fort Saskatchewan limits.
 •  Fort Centre Park Trail Closures in effect August 26, 2019 - October 1, 2022
 •  More Project Information


Neighbourhood Rehab – 101 Street

 •  Work to replace water, sewer and road infrastructure from 101 Ave to 99 Ave
 •  Work has been deferred to 2021


Neighbourhood Rehab – 108 Street

 •  Design work to replace water, sewer and road infrastructure on 108 Street from 101 Ave to the end of 108 Street will start in 2020. Construction is scheduled for 2021.


Old Gaol Bridge Closure

 •  Pedestrian Bridge over Highway 15 will be closed for railing replacement to meet current safety standards.
 •  The bridge will be be closed from October 19 to November 2, 2020 weather permitting.


Pointe Aux Pins Road Widening

 •  The project will widen Point Aux Pins road from Wilshire Blvd to Range Road 231. This will bring the road up to the City’s urban standard and provide an asphalt trail on the north side of the road.
 •  Stripping is complete. Work on the road base is complete.
 •  Surface work is underway
 •  Waterline installation to Pointe Aux Pins Residents is underway


River Road Slope Stabilization

 •  Tender to stabilize the slope adjacent to River Road (west of Keyera) is posted and closes Oct 8th


Sportsplex Ice Plant Replacement

 •  Contractor has been hired to replace the ice plant. Ice plant is scheduled to be replaced in early October
 •  Work on the room modifications for the new ice plant are underway


Sump Pump Retrofit Program

 •  Work has been deferred to 2021


Veterans Way Corridor Widening

 •  Detailed design work to add an additional lane on Highway 15 from 101 Street to the Highway 15/21 intersection is underway.