Construction Updates – November 19, 2026

119 Street Water Line Extension

  • Construction to extend the water line along 119 Street, west of Veteran’s Way, is continuing
  • Construction is planned to be completed in the fall of 2026
     

125 Street Road Upgrades

  • 125 Street from Highway 15 to Township Road 550 is being re-built. The road will be closed during construction.
  • Work is underway
  • Paving will be complete the week of November 16, 2026
     

2026 Bus Stop Installation

  • Work is complete
     

Bike Skills Park

  • The Bike Skills Park will be located north of the Dow Baseball Fields
  • Work on the wood features, concrete pads, and site amenities will be completed in 2026
  • Grading work for the pump tracks and landscaping will be completed in spring 2027
     

City of Fort Saskatchewan Entrance Signs

  • This project includes the replacement and relocation of the three City entrance signs
  • Design of signs is underway
     

Helmuth Ritter Fire Station

More information on the Helmuth Ritter Fire Station project

  • Detailed design is underway
  • Work on site will resume in spring 2027
     

Highway 15 – Right-in / Right-out

  • A new right-in / right-out is being installed along Highway 15 just north of 125 Street
  • Work is underway. Lane closures are expected throughout construction.
     

Neighbourhood Rehabilitation Program

Neighbourhood Rehabilitation is an annual program that ensures that the City's neighbourhood infrastructure meets current standards and is not at risk of failure due to deteriorating conditions.

More information on the Neighbourhood Rehabilitation Program and Projects

Neighbourhood Rehabilitation – 104 Street from 98 Avenue to 99 Avenue

  • Design is underway
  • Construction to occur in 2027

Neighbourhood Rehabilitation – 106 Street from 101 Avenue to 102 Avenue

  • Design is underway
  • Construction to occur in 2027

Neighbourhood Rehabilitation – 109 Street from 100 Avenue to 101 Avenue

  • Design is underway
  • Construction to occur in 2027
     

New Aquatics Facility Project

More information on the New Aquatics Facility Project

  • Forms for the walls of the technical corridor are installed. Work for the suspended slab for the corridor is underway.
     

Parks Naming Signs

  • Work to modify signs is underway
  • Locations include:
    • Don Westman Park
    • Petroski Park
    • Dr. Walter Buck Park
    • Raymond Truscott Park
       

Southfort Drive and Southfort Boulevard Widening

  • Design is underway
  • Construction is planned for 2027
      

Water Tower Refurbishment

  • Work is underway
  • Tarping is complete
     

F3Networks Fibre Optics Installation

  • This is not a City-led project
  • For concerns regarding F3Networks fibre optics installation, and up-to-date information, please contact F3Networks Fibre Optics Customer Care Service by calling 778-200-9100 or emailing Customerservice@F3Networks.ca